MOW WEEKLY UPDATE



6-27-2012

Hello all,

We will start removing the east rail Thursday night (6-28) as there will be no traffic to the shops or cars to Setzer on the 4th.

So that gives us from June 28 till July 10 to work on the east rail.

The switch ties will ship the second week of July.

We will need a lot of help to get this completed. We will be working Thursday and Saturday, Thursday starting at 5pm and Saturday at 8am.

Come out and have fun constructing a switch!

See you out on the line,
Alan, Chris and Sandy